We received a call from Paul around 9:00AM on Monday, August 4, informing us National Grid had attached the meter and connected our cable to the transformer. In other words, it’s (a)live!
The 70×32 frost wall foundation was dug extra wide, in case of collapse due to adverse weather conditions before the masons come to form and pour the footings and 4′ frost wall.
Main leach line to distribution box with three 50′ leach lines, plus 50% expansion, as per Washington County code.
A 20′ run with clean out, was installed for the RV. Having an easy-access dump station will be a big time saver. Thanks, Paul! The septic system passed inspection on August 5. |